April 18 |
|
|
An empty shell. From the front door, to the back.
|
An empty shell. From the front door, to the back.
|
An empty shell. Front doors, from the back.
|
|
|
|
April 27 |
|
|
Walls for the consulting rooms are going up!
|
Slab has been cut to lay the plumbing!
|
A veritable forest of steel wall studs
|
|
|
|
April 29 |
|
|
The back side of the consultation rooms
|
Looking into surgery (through a pesky beam)
|
These glassed-in runs will be perfect!
|
|
|
|
May 7 |
|
|
Progress is being made with sheetrock
|
The two towers are coming along nicely
|
Electricians and plumbers have been here
|
|
|
|
May 13 |
|
|
Plumbing rough-in complete!
|
Consultation rooms moving along…
|
Oxygen to cages and treatment islands!
|
|
|
|
May 19
|
|
|
Radiology has been insulated! Need to move that O2 line…
|
Masons have been working hard on the runs for larger dogs…
|
More sheetrock going up everywhere. It’s getting dark in here!
|
|
|
|
May 23
|
|
|
Waiting room looks good, lots of natural light. Fixtures coming along.
|
Treatment looks better with sheetrock, but bad light for pictures…
|
Masonry in the kennels is done, next comes the epoxy floor!
|
|
|
|
May 31
|
|
|
Painters started taping over the Memorial Day weekend. More tape & bed to come…
|
Light fixtures for the waiting room are shaping up! Has to come down for painting, though…
|
Surgery room! Wall-mount anesthesia, active waste gas removal, central suction!
|
|
|
|
June 6
|
|
|
Air conditioning ductwork, ceiling grid
|
Drywall tape & bed behind cages
|
Air conditioning for waiting area
|
|
|
|
June 10
|
|
|
Client bathroom tiles look great!
|
Let there be light (and air conditioning)!
|
Surgery room, walls ready for texture
|
|
|
|
June 14 |
|
|
Tile is done in front bathroom!
|
Sign being installed today!
|
Walls textured, switches & outlets in…
|
|
|
|
June 14 (again) |
|
|
 |
 |
 |
|
|
|
June 17 |
|
|
Epoxy floors in the kennel are done!
|
Painters are here! No more white!
|
Doors get installed this weekend!
|
|
|
|
June 21 |
;nbsp |
|
Treatment painted!
|
Hallway painted
|
Doors installed!
|
|
|
|
June 28 |
|
|
Consultation tables going in…
|
Cabinets filling the treatment room
|
Surgery cabinets installed, looking good…
|
|
|
|
June 29 |
|
|
Cabinets between cages for pumps
|
Treatment room is taking shape…
|
Surgery is easier when you have a table!
|
|
|
|
July 6 |
|
|
Easily-cleaned cages, complete with fittings for oxygen & nebulization
|
Surgery doors installed today. Keeps surgery clean (that’s important)
|
Kennels getting glassed in, soundproofing but patients always visible
|
|
|
|
July 14 |
|
|
Cages going into their places…
|
X-ray table & system installed
|
Wall-mount anesthesia machines!
|
All of the cages in their places…
|
Tub table installation and plumbing & anesthesia
|
The kennel runs have gates now!
|